Independent Connections Provider
Mezzanine Floor and Fitout Works
Kislingbury – Northampton
A rapidly growing connections provider for the electric, gas & solar industry contacted T2 Storage Solutions for its proposed Warehouse Refurbishment and Office Fit-Out in a recently purchased an warehouse in Northampton.
Our client had a very limited budget therefore works were completed in two phases to help our client financially.
Phase one cosisted of a new mezzanine floor, including a ground floor office alongside alterations to their existing warehouse pallet racking systems.
Phase two involved the installation of new offices on the recently installed first floor level.
We worked together with our client to ensure both phases were completed within the agreed programmes and to budget.
“T2 were one of several contractors we contacted to tender for the refurbishment of our new head office located on Brackmills Industrial Park in Northampton. They clearly understood our brief and provided a professional and detailed response to all our requests. Having then retained T2 they proceeded to carry out the works to an extremely high standard, on time and in budget. We were very pleased with their work and would not hesitate to recommend them to others.“
Debbie – Director
Works Included:
- Full Design & Turnkey Project Management.
- Pallet Racking Alteration Works
- 115m2 – Mezzanine Floor for Office Use (3.5kN/m2) designed to L/360 Deflection Limit
- One Hour Fire Protection to Underside of Mezzanine Floor Structure.
- Steel Fabrication – New Stairs and Cat-ladder.
- Wall Lining & Decoration Works
- Office Design & Office Partitioning.
- New Fire Rated Doors and Double Glazed Windows with Integral Blinds
- Teapoint Installation
- Plumbing Works
- Office Fit Out & Office Dilapidation Works
- Air Conditioning & Fresh Air Ventilation
- New Carpets & Flooring Works
- Suspended Ceilings
- Electrical Works – Including New lighting, Power & Data